Successful Workover of Well A-4 in Zaafarana Field

February 6, 2012

Related to:

On January 8, 2012, the Rig approached the PF to fish the stuck ESP Pump. The workover was successfully completed and put on production on February 6, 2012. A larger pump was installed with a more capacity, which in return increased oil production to 1,900 bopd—a rate that is higher than the initial expectations for the well’s production.